Firewise October 2025 Update

Firewise updated information as of October 13, 2025

RPFD Fire -October 2025.docx

 

*May 2nd ODF Chipping stopped at 14 properties

Total of 66 hours

6 ODF staff

6 FW partners (committee and community members)

3 Dump Trailers

 

*Quarry pile was pushed September 5th

 

*2025 FW reporting due November 17th

FW Committee is asking all residents to turn in their

In-Kind-Sheets by NOV 1

 

*Completed Grant Mitigation for High Rated Properties

31 properties in Varney Creek

16 properties

Odessa currently under mitigation

$73K spent at this point

Thank you to our contractor, Mark Moore!

 

Next areas will be Moderate in the Mountain Lakes Subdivision and parts of Rocky Point proper

 

Weather will play a part in mitigation for the balance of this year

 

Project completion date June 30, 2026

Committee:  Jerry Higgins, Diana Newdall, Del Ramsdell, Steve McKee, Greg Hoskins

Rod & Linda Golart, Ellen Fall